QuestionI am posting again for the missing part Assuming there are 10, 10,… I am posting again for the missing partAssuming there are 10, 10, 1, and 2 worker for groups 1, 2, 3, and 4, respectively. For each worker, a total of 6 operation, from Op1 to OP6 below, are required. down below shows the processing time of each operation for each group. Each operation is available 8 hours per day.Table 1. Treatment times (in minutes) for each patient-groupGroup OP1 OP2 OP3 OP4 OPT5 OP6 1 30 20 30 10 20 202 20 10 10 20 30 203 10 10 5 20 5 104 5 20 10 5 5 5Which treatment is the bottleneck, imp.utilization&utilization?How would the process capacity chnge if the available time of operation 5 is increased from 8 hours to 9 hours per day?Engineering & TechnologyIndustrial EngineeringOperations Management MBA 7511